3-19. Reassembly.  To reassemble the test set, refer to figure 3-7
k.  Apply protective coating to all repaired exposed areas.
and proceed as follows:
3-18. Repainting and Refinishing
WARNING
a.  Refinishing processes should restore equipment to original
appearance and as-in-new-standards. Minor damage to finishes, such
Ensure test set is disconnected from power
as small scratches, require touchup painting of the affected area only.
source before attempting reassembly. DEATH
Major surface damage requires complete repainting.
ON CONTACT or serious injury may result if
b.  Test Set TS-3630/GRA-114 is painted in accordance with
safety precautions are not observed.
military specification MIL-F-14072, Finish No. 513. IW. Use this
CAUTION
material if the entire case is stripped and refinished. For nicks,
Always read over and be sure you understand
scratches, or small areas which have peeling, use any matching paint
the instructions before attempting reassembly.
or finish listed in SB 11-573.
Use the illustrations to locate parts and
NOTE
subassemblies of the unit to be reassembled.
Touchup or new finish should be applied as
a.  Ensure POWER switch is in OFF position and ac power
prescribed in TB 43-0118.
cord is disconnected from power source.
b.  Carefully install panel assembly (2) into case assembly (3).
c.  Install four screws (1) into panel assembly.
Section V. TESTING PROCEDURES
d.  Perform each test step in sequence. Starting at step 1,
3-20. General
perform all the actions listed in the "Control Settings" columns for test
a.  The following testing procedures are necessary to verify the
equipment and equipment to be tested, ensuring the controls are set
performance standards for Test Set, Crystal Module TS3630/GRA114
accurately. Then perform all the actions listed in the test procedure
for general support level maintenance as authorized by the
column and verify the correct indication listed in the performance
maintenance allocation chart. If a part, subassembly, component, etc.,
standard column.
does not meet the performance standard, the fault should be isolated
3-21. Physical Tests and Inspection
and corrected using the troubleshooting, disassembly and repair
a.  Test Equipment and Inspection. No test equipment or
sections of chapter 3 of this manual. The SMR recoverability code of
materials are required.
the  affected  part  should  be  determined  by  consulting  TM
b.  Test Connections and Conditions.
115895109720P and TM 115895109740P.
(1) Remove any connections to test set.
b.  Insure all applicable MWO's have been done. Refer to DA
(2) Disassemble test set and probe amplifier (para 3-15).
Pam 310-1 for a listing of current MWO's.
c.  Procedure. Refer to table 3-6 for correct procedures.
c.  Use the test equipment and materials listed for each test.
Perform the test connections and conditions listed before proceeding
to the actual test.
Table 3-6. TS 3630/GRA-114 Physical Test and Inspection
Step
Control settings
no.
Test equipment
Unit under test
Test procedure
Performance standard
N/A
Controls may be
a. Inspect all exterior surfaces for stains,
a. Surfaces shall be free of
set in any posi-
fungus and corrosion.
stains, fungus and
tion
corrosion.
b. Inspect case for dents, cracks and general
b. Case shall be free of
structural damage.
Structural damage.
c. Inspect painted surfaces for scratches and
c. All painted surfaces shall be
cracked or peeling paint.
free of scratches which
penetrate the paint, and
cracked or peeling paint.
d. Inspect screws, nuts and bolts for loose-
d. All screws, bolts and nuts shall
ness
be tight; none shall be
missing.
e. Inspect front panel switches for loose-
e. Switch knobs shall be tight and
ness, missing knobs and normal switch
mechanical action normal.
action.
f.  Inspect front panel indicators for burned-
f. Indicator bulb shall be installed
out or missing bulbs.
and in working order.
g. Inspect fuse and fuseholder for proper
g. Fuse shall be correct size (A),
size, burned out, or missing fuse
installed and in working order.
h. Inspect electrical components and print-
h. Electrical components and printed
ed circuit cards for signs of heat damage
circuit cards shall be free of
heat damage.
3-21